Year 3

Working Plan for project year 3
  15 Jan – 2023  to 14-jan-2024

WP5 Implementation  

5.3 Large scale Implementing IMCert blended programme.

5.3

WP6 Evaluation & Quality assurance

6.1: QCMP strategy

6.2: Reports of quality Internal and external assessment

6.1
6.2

WP7 Dissemination  

7.1: Dissemination, and sustainability strategic plan

7.2: Project’s Website & TLC website

7.3: E-Tool Kit Integration

7.4:  National & international Conferences.

7.5: Publications.

7.1 7.2 7.3 7.4 7.5

WP8 Management

 8.1:  Project management and communication plans

 8.2:  Risk plan

 8.3: Biannual report

 8.4: Financial management

 8.5; Scheme of workshops, meetings and events

 8.6; Final report

8.1
8.2
8.3
8.4
8.5
8.6